Analisis Manajemen Risiko pada Proyek Konstruksi (Studi Kasus: Pembangunan Gedung Rumah Sakit Hamori Subang)

Authors

  • Shafa Dewintha Universitas Jendral Achmad Yani
  • Waluyo Hatmoko Universitas Jendral Achmad Yani

DOI:

https://doi.org/10.55893/jt.vol25no1.829

Keywords:

risk management, construction project, severity index, probability–impact matrix , hospital

Abstract

Construction projects are characterized by high levels of uncertainty and are vulnerable to various risks that may affect project performance. This study aims to analyze risk management in the construction project of Hamori Hospital Building, Subang Regency, by identifying potential risks, assessing risk levels, and determining appropriate mitigation measures. The research employed a quantitative descriptive approach using primary data collected through questionnaires and interviews with respondents directly involved in the project, as well as secondary data obtained from project documents and literature studies. Risk identification was conducted using a Guttman scale, while risk assessment was carried out using the Severity Index (SI) method to determine the probability and impact of risks. The risk level was further categorized using a Probability–Impact Matrix to identify dominant risks. The results of the study showed that there were five dominant risks in the high category, namely extreme rain, lack of K3 signs, lack of K3 supervision, changes in the schedule of work implementation, and lack of control over the schedule of work implementation. These risks require priority mitigation to minimize their impact on project implementation.

Author Biographies

  • Shafa Dewintha, Universitas Jendral Achmad Yani

    Master of Civil Engineering, Faculty of Engineering

  • Waluyo Hatmoko, Universitas Jendral Achmad Yani

    Master of Civil Engineering, Faculty of Engineering

References

A. Kassem, M., Khoiry, M. A., & Hamzah, N. (2019). Using probability impact matrix (PIM) in analyzing risk factors affecting the success of oil and gas construction projects in Yemen. International Journal of Energy Sector Management, 14(3), 527–546. https://doi.org/10.1108/IJESM-03-2019-0011

Afiq, M. (2021). MANAJEMEN RISIKO PADA PROYEK PEMBANGUNAN GEDUNG ASRAMA MAHASISWA UIN WALISONGO TAHUN 2021. Akselerasi : Jurnal Ilmiah Teknik Sipil, 3(1). https://doi.org/10.37058/aks.v3i1.3561

Ahmad Rizky Zaidan, Koosdaryani Soeryodarundio, & Setiono Setiono. (2024). Analisis Manajemen Risiko Proyek dengan Metode Severity Index (SI) pada Proyek Pembangunan Gedung X Kota Surakarta. Globe: Publikasi Ilmu Teknik, Teknologi Kebumian, Ilmu Perkapalan, 2(3), 211–221. https://doi.org/10.61132/globe.v2i3.501

Gulindo, H. A. (2021). Analisis Manajemen Risiko Yang Mempengaruhi Kontraktor pada Pelaksanaan Proyek Jalan dan Gedung di Kabupaten Malinau-Kalimantan Utara. Jurnal Indonesia Sosial Teknologi, 2(5), 805–815. https://doi.org/10.36418/jist.v2i5.145

Honesti, L., & Ramadhan, J. (2021). IDENTIFIKASI MANAJEMEN RISIKO KINERJA BIAYA PADA PROYEK KONTRUKSI GEDUNG DI PROVINSI SUMATRA BARAT (Dilihat dari sudut pandang kontraktor). Rang Teknik Journal, 4(1), 68–75. https://doi.org/10.31869/rtj.v4i1.2030

Iqbal, S., Choudhry, R. M., Holschemacher, K., Ali, A., & Tamošaitienė, J. (2015). RISK MANAGEMENT IN CONSTRUCTION PROJECTS. Technological and Economic Development of Economy, 21(1), 65–78. https://doi.org/10.3846/20294913.2014.994582

Jayasudha, K., & Vidivelli, B. (2016). ANALYSIS OF MAJOR RISKS IN CONSTRUCTION PROJECTS. 11(11).

Kahandanie, F., & Mahfud, M. (2020). Manajemen Risiko Konsultan Perencana Kontruksi Di Kota Balikpapan. Jurnal Kacapuri : Jurnal Keilmuan Teknik Sipil, 3(2), 71. https://doi.org/10.31602/jk.v3i2.4068

Maharani, S. A., Sari, S., As’adi, M., & Saputro, A. P. (2022). Analisis Risiko Pada Proyek Konstruksi Perumahan Dengan Metode House of Risk (HOR) (Studi Kasus: Proyek Konstruksi Perumahan PT ABC). Journal of Integrated System, 5(1), 16–26. https://doi.org/10.28932/jis.v5i1.3996

Maulana, A. W., & Santosa, B. (2020). Risk Management Analysis of Building Construction Project in the Jakarta City. Jurnal Fondasi, 9(1). https://doi.org/10.36055/jft.v9i1.7199

M.Hendra Aulia Rahman & Hanie Teki Tjendani. (2022). Identifikasi Risiko Pelaksanaan Pembangunan Proyek Gedung Highrise Building Di Hotel Grand Dafam Signature Yogyakarta. PADURAKSA: Jurnal Teknik Sipil Universitas Warmadewa, 11(2), 177–185. https://doi.org/10.22225/pd.11.2.5336.177-185

Oktaviani, O., Susetyo, B., & Kusumo Bintoro, B. P. (2021). Risk Management Model using Cause and Effect Analysis in Industrial Building Project. International Journal of Research and Review, 8(8), 227–235. https://doi.org/10.52403/ijrr.20210832

Project Management Institute. (2008). A Guide to the Project Management of Body Knowledge (PMBOK Guide). Project Management Institute.

Purba, I. Y. & Rhini Wulan Dary. (2021). Analisis Risiko Terhadap Biaya, Mutu Dan Waktu Pada Proyek Pembangunan Rumah Susun Kota Tanjung Balai Provinsi Sumatera Utara 1 TA. 2020. Jurnal Ilmiah Teknik Sipil Agregat, 1(2), 72–84. https://doi.org/10.51510/agregat.v1i2.519

Rumimper, R. R., Sompie, B. F., & Sumajouw, M. D. J. (2015). ANALISIS RESIKO PADA PROYEK KONSTRUKSI PERUMAHAN DI KABUPATEN MINAHASA UTARA.

Samudra, A. R., Hatmoko, J. U. D., & Wibowo, M. A. (2023). Analisa Faktor Risiko Prioritas pada Proyek Konstruksi Jembatan. Syntax Literate ; Jurnal Ilmiah Indonesia, 8(7), 5040–5049. https://doi.org/10.36418/syntax-literate.v8i7.12944

Septiaji, A. I., Jayady, A., & Suryani, F. (2025). Managing Cost and Schedule Risks in High-Rise Building Projects: A Case Study from Jakarta, Indonesia. Journal of Architecture and Civil Engineering, 10(8), 01–09. https://doi.org/10.35629/8193-10080109

Suriyadi, S., & Azmi, F. (2022). PENGEMBANGAN MANAJEMEN RESIKO PADA INSTANSI PENDIDIKAN. Warta Dharmawangsa, 16(3), 543–553. https://doi.org/10.46576/wdw.v16i3.2246

Wally, S. N., Jamlaay, O., & Marantika, M. (2022). ANALISIS MANAJEMEN RISIKO PADA PROYEK PEMBANGUNAN GEDUNG LABORATORIUM TERPADU DAN PERPUSTAKAAN MAN 1 MALUKU TENGAH. Menara: Jurnal Teknik Sipil, 17(2), 61–69. https://doi.org/10.21009/jmenara.v17i2.27124

Additional Files

Published

2026-07-06

How to Cite

Analisis Manajemen Risiko pada Proyek Konstruksi (Studi Kasus: Pembangunan Gedung Rumah Sakit Hamori Subang). (2026). Jurnal Teknik: Media Pengembangan Ilmu Dan Aplikasi Teknik, 25(1), 71-79. https://doi.org/10.55893/jt.vol25no1.829

Similar Articles

11-20 of 264

You may also start an advanced similarity search for this article.