Evaluasi Kinerja Proyek Peningkatan Jaringan Irigasi Tukad Petanu Berdasarkan Earned Value Analysis

Authors

  • Ni Putu Indah Yuliana Politeknik Negeri Bali
  • Ni Kadek Sri Ebtha Yuni Politeknik Negeri Bali

DOI:

https://doi.org/10.26874/jt.vol20no1.147

Keywords:

Earned Value Analysis , Budgeted Cost Work Schedule, Budgeted Cost Work Performance, Actual Cost Work Performance

Abstract

The achievements review of Tukad Petanu irrigation network improvement project still uses traditional cost management concept so that the evaluation based on value analysis needs to be done. The purpose of the research’s is to analyze project’s cost and time performance based on earned value analysis. This research uses quantitative descriptive with earned value analysis. Based on analysis, from 1st to 8th month the value of Budgeted Cost Work Performance (BCWP) is above Budgeted Cost Work Schedule (BCWS) and ends at the same point in 9th month so it categorized run faster 6,52% of planned time and ends according to planned time. The Actual Cost Work Performance (ACWP) value is below the BCWP so the actual costs are less than planned costs, which is 21.14% of planned costs. Analysis of cost and time variance based on cumulative have a positive value (+), shows the work is run faster than planned and the costs are smaller than the budget. The cumulative cost and time performance index have an average Cost Performance Index (CPI) of 1.21 and an average Schedule Performance Index (SPI) of 1.02 so the project runs faster than planned time and costs are smaller than planned budget.

Author Biography

  • Ni Kadek Sri Ebtha Yuni, Politeknik Negeri Bali

    Jurusan Teknik Sipil

References

Ahuja, H., Dozki, S. P., & Abourizk, S. M. (1994). Project Analysis Techniques in Planning and Controlling Construction Project. New York: John Willey & Sons.

Bulo, M. W., Balaka, R., & Sriyani, R. (2013). Pengaplikasian Metode Earned Value pada Pengendalian Waktu Terhadap Biaya (Studi Kasus: Proyek Penggantian Jembatan Sungai Langkolome Cs Kabupaten Muna). Jurnal Stabilita, 1(3), 359-372.

Ervianto, W. I. (2005). Manajemen Proyek Konstruksi. Yogyakarta: Andi Offset.

Febriani, N. F. (2018). Analisa Kinerja Terhadap Waktu dan Biaya dengan Metode Earned Value Analysis pada Pembangunan Gedung Auditorium IAIN Samarinda. Jurnal Keilmuan dan Aplikasi Teknik Sipil, 1(1), 1813-1826.

Ghozali, A. A., Harimurti., & Hasyim, H. (2017). Monitoring Proyek Rehabilitasi Saluran Irigasi Ngrejo dengan Metode Konsep Nilai Hasil Berdasarkan Time Based dan Progress Based. Jurnal Mahasiswa Jurusan Teknik Sipil Universitas Brawijaya, 1(1), 501-508.

Maromi, M. I., & Indryani, R. (2015). Metode Earned Value untuk Analisa Kinerja Biaya dan Waktu Pelaksanaan pada Proyek Condotel De Vasa Surabaya. Jurnal Teknik ITS, 4(1), 54-59.

Nurhayati. (2010). Manajemen Proyek. Yogyakarta: Graha Ilmu.

Nurtsani, R. A., Septiadi, D. R., & Suharyanto, S. (2017). Pengendalian Biaya dan Waktu Proyek dengan Metode Konsep Nilai Hasil (Earned Value). Jurnal Karya Teknik Sipil, 6(4), 460-470.

Soeharto, I. (2001). Manajemen Proyek (Dari Konseptual Sampai Operasional). Jakarta: Erlangga.

Sudipta, I. G. (2013). Studi Manajemen Proyek Terhadap Sumber Daya pada Pelaksanaan Proyek Konstruksi (Studi Kasus: Pembangunan Villa Bali Air). Jurnal Ilmiah Teknik Sipil, 17(1), 73-83.

Additional Files

Published

2021-06-30

How to Cite

Evaluasi Kinerja Proyek Peningkatan Jaringan Irigasi Tukad Petanu Berdasarkan Earned Value Analysis. (2021). Jurnal Teknik: Media Pengembangan Ilmu Dan Aplikasi Teknik, 20(1), 21-30. https://doi.org/10.26874/jt.vol20no1.147

Similar Articles

1-10 of 54

You may also start an advanced similarity search for this article.