Analisa Hasil Forensik Penerapan Manajemen Waktu pada Proyek Jalan Di Ruas Rancapanggung – Sarinagen Kabupaten Bandung Barat

Authors

  • Nurwahyono Universitas Jenderal Acmad Yani
  • Antono Damayanto Universitas Jenderal Acmad Yani

DOI:

https://doi.org/10.55893/jt.vol23no2.651

Keywords:

Importance Index, Influence Index, Frequency Index, Time Management , Construction Project

Abstract

Time management is a crucial process to ensure projects are completed on time, which focuses on planning and scheduling project activities to make them faster and more efficient. This research explores the application of time management in the Road construction project in Rancapanggung - Sarinagen, West Bandung Regency, implemented by PT Basuki - Lesindo, KSO. The purpose of this study is to identify and understand the factors that hinder time management and the dominant factors that influence it. The research method used a quantitative approach through questionnaires to 21 respondents, followed by descriptive analysis and ranking of respondents, and validation through interviews. The results showed four main barriers in the implementation of time management, insufficient number of work tools (dominant factor with 44.5%), inappropriate construction methods (43%), lack of communication and coordination among the project implementation team (41.5%), and materials that are damaged or not according to specifications (41.4%). The most dominant factor in the delay was the insufficient number of work tools, indicating the importance of adequate resource allocation.

Author Biographies

  • Nurwahyono, Universitas Jenderal Acmad Yani

    Civil Engineering

  • Antono Damayanto, Universitas Jenderal Acmad Yani

    Civil Engineering

References

Amoatey, C. T. (2017). Exploring critical road project delay factors in Ghana. Journal of Facilities Management, 15(2), 110-127.

ARITEKIN, A. R. (2024). Analisis Faktor-Faktor Pekerjaan Proyek Prasarana Jalan Lingkungan. Konstruksi: Publikasi Ilmu Teknik, Perencanaan Tata Ruang dan Teknik Sipil, 38-54.

Bhatt, N. &. (2020). Evaluation of success and risk factors for highway project performance through integrated analytical hierarchy process and fuzzy interpretive structural modelling. International Journal of Construction Management, 20(6), 65.

Deep, S. B. (2022). Critical factors influencing the performance of highway projects: an empirical evaluation. Buildings, 12(6), 849.

Ghozali, I. (2018). Aplikasi Analisis Multivariate SPSS 25. Semarang: Universitas Diponegoro.

Gómez-Cabrera, A. S.-B.-D.-T. (2020). Identification of factors affecting the performance of rural road projects in Colombia. Sustainability, 12(18), 7377.

Leo-olagbaye, F. &. (2018). An evaluation of risk factors and their impact on road project. Journal of Construction Business and Management, 2(2), 24-35.

Ojha, R. &. (2017). Integrated impact of highway infrastructure, labour productivity and circular material consumption on Indian manufacturing growth: A system dynamics perspective. Journal of Advances in Management Research, 14(4), 527-542.

PUPR, P. M. (2016). Indonesia Paten No. No. 28/PRT/M/2016.

Rizal, A. H., Manek, P. K., & Bella, R. A. (2023). ANALISIS FAKTOR-FAKTOR PENYEBAB PERBEDAAN WAKTU ANTARA PERENCANAAN DAN REALISASI DI LAPANGAN PADA PROYEK KONSTRUKSI. Jurnal Teknik Sipil, 12 No. 2, 159-172.

Sugiyono. (2017). Metode Penelitian Kuantitatif, Kualitatif, dan R&D. Alfabeta.

Additional Files

Published

2025-01-04